Permit basics

Building Permit Inspections: What Inspectors Check and When

A permit is only half the process. The inspections are where the city actually checks the work, and the final inspection is what closes the permit. Here is how inspections work under the model code and in the cities we track.

Updated 6 min readLast checked 5 official sources

A construction worker in a hard hat on a timber house frame
Photo: Unsplash. Illustrative only; it does not show a specific permitted project.

Short Answer

Most permits need several inspections, typically footing, framing, rough-in for each trade and a final. Your contractor schedules each one, often 24–48 hours ahead, and the work can't be covered until it passes. The final inspection closes the permit.

Key Takeaways

  • IRC R109 requires inspections at key stages so concealed work is seen before it is covered.
  • Typical stages are footing and foundation, rough-in (framing, electrical, plumbing, mechanical), insulation where required, and final.
  • The permit holder is responsible for scheduling inspections and giving access; work must not be covered before approval.
  • A permit that never gets a final inspection stays open and can expire, which can cause trouble at sale time.
  • Cities publish their own inspection guidelines; Baltimore and Orlando are examples.

Quick Facts

Typical stagesFooting, framing, rough-ins, insulation, final
Philadelphia notice48 hours before work and before each inspection
Orlando roofsDry-in (code 125) and final
AustinPermit expires on day 181 without an inspection

From our city pages and each city's open permit data (refreshed October 30, 2026).

Why Inspections Exist

Most of what makes a house safe is hidden: footings, framing connections, wiring, gas lines and drain slopes. Inspections exist so that a trained official sees that work before drywall, roofing or soil covers it. The IRC's administration chapter sets the framework: R109 lists required inspections, and R110 covers the certificate of occupancy for new dwellings. If work is covered too early, the inspector can require it to be uncovered.

Step-by-Step: What to Do

  1. Find which inspections your permit requires.
  2. Schedule each before covering the work.
  3. Have the permit and approved plans on site.
  4. Fix any corrections and request a re-inspection.
  5. Pass the final and keep the record.

The Usual Inspection Stages

  1. Footing and foundation: after excavation and forms or reinforcement are in place, before concrete is poured. Common for decks, additions and ADUs.
  2. Underground or under-slab: plumbing or electrical that will be buried.
  3. Rough-in: framing plus rough electrical, plumbing and mechanical, before walls are closed. Trades may be inspected separately.
  4. Insulation or energy: where the local code requires it.
  5. Final: when the work is complete. A passed final closes the permit.

Simple jobs need fewer inspections. A re-roof may have a mid-roof or dry-in inspection and a final; Orlando's residential roof permit, for example, includes a dry-in inspection before the final. An HVAC change-out may need only a final.

What Inspectors Look For

Inspectors compare the work with the approved permit and the code. Typical checks include:

  • The work matches the permit scope and any approved plans.
  • Structural elements: footing depth, beam and joist sizes, connectors and fasteners.
  • Fire and life safety: smoke and carbon monoxide alarms, egress, fire separation.
  • Electrical: correct wire sizes, breakers, grounding and protection devices.
  • Plumbing and gas: materials, slopes, venting and pressure tests.
  • Mechanical: equipment sizing, venting, clearances and refrigerant connections.

Keep the permit card visible and approved plans on site. Many cities require it, and it speeds up every visit.

Scheduling and Passing an Inspection

The permit holder, usually the contractor, requests each inspection through the city's portal or phone line. Baltimore publishes inspection guidelines that explain what must be ready at each stage. To pass the first time:

  • Request the inspection only when that stage is fully complete.
  • Make sure someone can give the inspector access.
  • Have the permit number and approved plans ready.
  • Fix corrections promptly and request a re-inspection. Some cities charge re-inspection fees; amounts vary by jurisdiction.

The Final Inspection Closes the Permit

The final inspection is the step most often skipped, usually because the homeowner did not know it was needed or the contractor moved on. A permit without a final stays open in the city's records and, under rules like IRC R105.5, may expire. An open or expired permit can surface during a sale, as described in Selling a House with Unpermitted Work: Risks and Options. Before making the final payment to a contractor, ask for proof that the final inspection passed.

You can check this yourself in the permit record; How to Read a Building Permit Record explains the status codes.

If an Inspection Fails

A failed inspection is normal and simply means corrections are needed. The inspector leaves a list; the contractor fixes the items and requests a re-inspection. If you disagree with a decision, ask the department about its appeal process. Under the IRC, the building official can also issue a stop work order (R114) if work is unsafe or proceeding contrary to the code.

Preparing the Site for an Inspector

  • Access: clear paths to the work, ladders for roofs and attics, and pets secured.
  • Documents: the permit card, approved plans and any product installation instructions or engineering letters.
  • Visibility: do not cover framing, wiring, piping or footings that are due for inspection.
  • Completeness: the stage should be finished. Partial work often leads to a failed inspection and a re-inspection fee.
  • Safety: temporary guards on decks and stairs, and power safely off where the inspector needs to see live parts.

Remote and Video Inspections

Some departments offer virtual inspections for simple work, where the contractor or owner walks the inspector through the job on a video call. Availability and eligible work vary by jurisdiction; ask your department whether it offers them.

Keep the Records

Save inspection results with your house documents. They are the clearest evidence, years later, that the work was approved.

Inspection Rules in Three Cities

Philadelphia requires the inspector to be notified 48 hours before work and every inspection to be scheduled 48 hours in advance. Orlando requires a dry-in inspection on re-roofs; skipping it can mean removing roof covering. In Austin, canceled inspections and "failed/no work performed" results don't extend a permit's life.

Building Departments in the Cities We Cover

Rules in this guide vary by jurisdiction. These are the official departments that issue residential permits in the 15 cities we track, with the city's open-data source for permit records. Each city page shows the rules for roofing, HVAC, solar, fence and deck work.

CityIssuing departmentPermit records
Chicago, ILChicago Department of BuildingsChicago Building Permits
New York, NYNYC Department of BuildingsDOB NOW: Build – Approved Permits
Los Angeles, CALos Angeles Department of Building and Safety (LADBS)LADBS Building Permits Issued 2020–Present
Austin, TXCity of Austin Development Services DepartmentAustin Issued Construction Permits
Seattle, WASeattle Department of Construction and Inspections (SDCI)Seattle Building Permits
Orlando, FLCity of Orlando Permitting ServicesOrlando Permit Applications
Philadelphia, PAPhiladelphia Department of Licenses and Inspections (L&I)Philadelphia L&I Permits (Carto)
Baltimore, MDBaltimore City Department of Housing & Community Development (DHCD)Open Baltimore: DHCD Permits
Nashville, TNMetro Nashville Department of Codes and Building SafetyMetro Nashville Building Permits Issued
Raleigh, NCCity of Raleigh Permit and Development ServicesRaleigh Building Permits
San Francisco, CASan Francisco Department of Building Inspection (DBI)DataSF: Building Permits
New Orleans, LANew Orleans Department of Safety and PermitsNOLA Permits
Pittsburgh, PAPittsburgh Department of Permits, Licenses, and Inspections (PLI)WPRDC: PLI Permits
Cincinnati, OHCincinnati Department of Buildings & InspectionsCincinnati Building Permits
Kansas City, MOKansas City, MO City Planning & Development DepartmentKCMO Permits (CPD)

Before relying on any rule, read the department's current page or call its permit desk. Model-code sections cited here (such as IRC R105) are adopted locally, often with amendments.

Frequently Asked Questions

Who schedules building inspections?

The permit holder, usually the contractor. If you pulled the permit as an owner-builder, it is your responsibility.

What happens if I close the walls before the rough-in inspection?

The inspector can require you to open them so the work can be seen. Covering work before approval is a common, costly mistake.

How many inspections does a project need?

It depends on the permit. A deck or addition may need footing, framing and final inspections; an HVAC change-out may need only a final.

What happens if I never get a final inspection?

The permit stays open and may expire. Open permits often come up when you sell or refinance.

Do I need to be home for the inspection?

Someone must give the inspector access. Ask your contractor whether they will meet the inspector.

How far ahead do I schedule an inspection?

Rules vary. Philadelphia asks for 48 hours' notice; many cities allow next-day requests online.

Written and maintained by the Home Permit Guide Editorial TeamPlaceholder profile

Last updated

This is a placeholder editorial profile. A named reviewer with verifiable experience will be added here. Until then, every rule on this page links to the official government source it was checked against. Read our editorial policy.

Sources

Official sources checked on . Rules change; confirm with the department before you start work.

  1. ICC: 2021 International Residential Code, Chapter 1 (Scope and Administration) (codes.iccsafe.org)
  2. Baltimore DHCD: Permit Guidelines and Forms (baltimorecity.gov)
  3. City of Orlando: Apply for a Residential Roof Permit (orlando.gov)
  4. Philadelphia L&I: Start Right Guide (June 2026) (phila.gov)
  5. City of Austin: Accessory Dwelling Units (austintexas.gov)