Short Answer
Yes: rooftop solar needs at least an electrical permit in every city we track, followed by an inspection and the utility's approval before the system can run. Your installer normally handles the permit, but you should see it issued before panels go up.
Key Takeaways
- A permit and inspection are required before a system may produce power on the grid, according to the U.S. Department of Energy.
- Some cities treat solar as electrical-only: San Francisco exempts small rooftop systems from a building permit, and Nashville and New Orleans permit solar as electrical work.
- Fast tracks: Chicago Express Permits up to 13.44 kW inverter output; Seattle over-the-counter up to 12 kW; New Orleans requires SolarAPP+ review since March 1, 2025.
- New York City requires a licensed contractor and a Registered Design Professional for all solar work.
Quick Facts
| Cities compared | 8 |
|---|---|
| Permit usually required | 7: Chicago, New York, Austin, Orlando, Raleigh, New Orleans, Pittsburgh |
| Exempt, partly exempt or zoning only | 1: San Francisco (electrical permit) |
| Permits issued in the last 12 months | 8,922 across 8 cities; most in New York (5,493) |
| Median days to issue | 5 (New York) to 41 (San Francisco) |
| Official fees published | New Orleans |
From our city pages and each city's open permit data (refreshed October 30, 2026).
Three Approvals, Not One
A rooftop system usually needs three separate approvals: the local permit (building, electrical or both), a passed inspection, and the utility's interconnection approval. The Department of Energy notes that installation itself generally takes only a few days, while permits and inspections can take weeks to months. Ask your installer which of the three is holding things up if a project stalls.
City-By-City Solar Panel Permit Rules
These summaries come from the same official sources as our city pages and were last checked October 30, 2026. Permit counts are the city's own open-data records for the last 12 months.
Chicago: Yes
New small rooftop solar systems up to 13.44 kW inverter output can use Chicago's Express Permit Program, with drawings and calculations from an Illinois-licensed architect or structural engineer. Larger systems, roofs over 40 feet and some ballasted systems need a standard permit.
- Express Permit limit: 13.44 kW inverter output.
- Drawings and calculations by an Illinois-licensed architect or structural engineer are required.
- Associated battery storage is generally limited to 20 kWh under the Express route.
- Chicago issued 1,615 matching permits in the last 12 months, with a median of 10 days from application to issue.
Source: Chicago DOB Express Permit Program: Small-Scale Solar PV System · Full details: Chicago Solar Panel Permits
New York: Yes
No solar work can be done in New York City without a DOB work permit, a licensed contractor and a Registered Design Professional. Only solar landscape lights are exempt.
- A DOB work permit is required for every solar energy system.
- A licensed contractor and a Registered Design Professional are required.
- Solar landscape lights are the only exemption.
- New York issued 5,493 matching permits in the last 12 months, with a median of 5 days from application to issue.
Source: NYC DOB: Project Requirements for Owner – Solar System
Austin: Yes
Solar panels or solar shingles inside Austin city limits that interconnect to Austin Energy need a residential building permit. Systems in the ETJ use a separate auxiliary permit through the AB+C portal.
- Inside city limits: residential building permit.
- In the ETJ: separate solar permit through the AB+C portal.
- Interconnection with Austin Energy is part of the process.
- Austin issued 660 matching permits in the last 12 months, with a median of 9 days from application to issue.
Source: Austin DSD: Types of Permits · Full details: Austin Solar Panel Permits
Orlando: Yes
Orlando reviews residential solar with a Solar Plan Review Checklist, and the electrical work is permitted as 'New Solar' on the Electrical Permit Application.
- Electrical permit ('New Solar').
- Solar Plan Review Checklist applies.
- Contractors must hold a Florida license and be registered with the City.
- Orlando issued 176 matching permits in the last 12 months, with a median of 14 days from application to issue.
Source: City of Orlando: Permitting Checklists · Full details: Orlando Solar Panel Permits
Raleigh: Yes
Solar adds electrical wiring and equipment, which North Carolina excludes from the $40,000 permit exemption, so a rooftop solar system in Raleigh needs a permit.
- New electrical wiring and equipment are excluded from the exemption.
- Licensed electrical contractors must be named.
- Roof-mounted arrays may need structural review.
- Raleigh issued 11 matching permits in the last 12 months, with a median of 11 days from application to issue.
Source: N.C. General Statute 160D-1110 · Full details: Raleigh Solar Panel Permits
San Francisco: Electrical Permit
A small residential rooftop solar system on a building that isn't a designated landmark is exempt from a building permit in San Francisco, but an electrical or other permit may still be required. Registered contractors can apply for solar photovoltaic permits online.
- Small residential rooftop solar on non-landmark buildings: no building permit.
- An electrical permit or other permit may be required depending on the system.
- Solar PV permits can be issued online to registered contractors.
- San Francisco issued 423 matching permits in the last 12 months, with a median of 41 days from application to issue.
Source: SF.gov: Check if your construction project needs a permit · Full details: San Francisco Solar Panel Permits
New Orleans: Yes
Rooftop solar in New Orleans is permitted as an electrical permit, which only a contractor with a Class A City of New Orleans electrical license can obtain. Since March 1, 2025, applications need an approved SolarAPP+ plan review.
- Rooftop solar is classified as an electrical permit.
- Only Class A city-licensed electrical contractors can apply.
- An approved SolarAPP+ plan review PDF is required (since March 1, 2025).
- Official fees: Electrical (solar) permit: $40 + $3 per new circuit + $0.30 per service amp.
- New Orleans issued 244 matching permits in the last 12 months, with a median of 25 days from application to issue.
Source: City of New Orleans: Solar Permitting · Full details: New Orleans Solar Panel Permits
Pittsburgh: Yes
Roof-mounted and ground-mounted solar arrays need a residential electrical permit from PLI, plus a Zoning Development Review. Roof-mounted installs are limited to buildings with a valid certificate of occupancy.
- Solar PV arrays are an electrical permit work scope.
- Solar PV arrays also need a Zoning Development Review.
- Roof-mounted arrays need a building with a valid certificate of occupancy.
- Pittsburgh issued 300 matching permits in the last 12 months.
Source: Pittsburgh PLI: Residential Electrical Permit · Full details: Pittsburgh Solar Panel Permits
| City | Permit needed? | Permits (12 mo) | Median days to issue |
|---|---|---|---|
| Chicago | Yes | 1,615 | 10 |
| New York | Yes | 5,493 | 5 |
| Austin | Yes | 660 | 9 |
| Orlando | Yes | 176 | 14 |
| Raleigh | Yes | 11 | 11 |
| San Francisco | Electrical permit | 423 | 41 |
| New Orleans | Yes | 244 | 25 |
| Pittsburgh | Yes | 300 | Not published |
Step-by-Step: What to Do
- Check your roof's condition and age before signing; replace it first if needed.
- Confirm your installer holds the license your city requires (NYC, New Orleans and others require a licensed contractor).
- Your installer applies for the permit; ask for the permit number.
- Installation, then the city inspection.
- Apply for, or let the installer submit, utility interconnection; do not switch the system on until the utility gives permission.
Automated Permits With SolarAPP+
SolarAPP+ is an online tool funded by the Department of Energy that checks standard residential solar designs automatically. New Orleans requires an approved SolarAPP+ review for solar electrical permits applied for since March 1, 2025. Where a city uses it, a code-compliant design can be approved without waiting for a plan reviewer.
Roof Condition and Structural Review
Chicago's Express Permit requires drawings and calculations by an Illinois-licensed architect or structural engineer, and sends roofs over 40 feet and some ballasted systems to standard review. Pittsburgh only allows roof-mounted systems on buildings with a valid certificate of occupancy. If your roof is near the end of its life, the Department of Energy notes it can save money to replace it before installing; see Roof Replacement Permit Rules in 13 US Cities for that permit.
Permit Pages and Related Guides
Compare all solar cities on Solar Panel Permits by City, see a busy example on New York Solar Panel Permits, and read How Long Does a Building Permit Take? Real Timelines from 12 Cities for what drives review times.
Frequently Asked Questions
Do solar panels need a permit?
Yes, in every city we track. Some cities issue only an electrical permit for small rooftop systems.
How long does a solar permit take?
It varies. In our data the median from application to issue was 5 days in New York City, 10 in Chicago and 41 in San Francisco over the last 12 months.
Can I install solar panels myself?
Rules vary. New York City requires a licensed contractor and a Registered Design Professional, and New Orleans issues solar electrical permits only to Class A licensed electrical contractors.
How much is a solar permit?
New Orleans charges $40 plus $3 per new circuit and $0.30 per service amp for a solar electrical permit. Most cities we track do not publish a flat solar fee.
Do I need utility approval as well as a permit?
Yes. After the city inspection, the utility must approve the interconnection before the system can produce power on the grid.
Sources
Official sources checked on . Rules change; confirm with the department before you start work.
- U.S. Department of Energy: Permitting and Inspection for Rooftop Solar (energy.gov)
- U.S. Department of Energy: Step-by-Step Guide for Consumers Going Solar (energy.gov)
- NREL SolarAPP+ (automated solar permitting) (solarapp.nrel.gov)
- Chicago DOB Express Permit Program: Small-Scale Solar PV (linked above) (chicago.gov)
- NYC DOB: Project Requirements for Owner – Solar (linked above) (nyc.gov)
- Seattle SDCI Tip 420: Solar Energy Systems (seattle.gov)
- City of Orlando: Permitting Checklists (linked above) (orlando.gov)
- N.C. General Statute 160D-1110 (linked above) (ncleg.gov)